FAA rules for drone solar inspection
Most global vendor pages skip this, which is why US buyers distrust them. A commercial solar inspection flight in the United States sits under 14 CFR Part 107. The baseline checklist is short; the exceptions are where projects stall.
What FAA compliance actually requires on a solar site
The baseline, no waiver needed
A certificated remote pilot in command; aircraft registered; visual line of sight maintained; daylight or civil twilight with anti-collision lighting; at or below 400 ft AGL (or within 400 ft of a structure); Remote ID broadcasting, which has been required for operations since March 2024.
Where authorization enters
Controlled airspace needs an authorization, in practice through LAANC — relevant more often than people expect, because large arrays sit near regional airports. Operations over people, night work beyond the lighting rule, one pilot flying multiple aircraft, and beyond visual line of sight all need a waiver under §107.200 or the relevant section.
BVLOS and the Part 108 question
Routine beyond-visual-line-of-sight flight is the unlock for one-pilot coverage of a 500 MW site. The FAA published its Part 108 proposed rule in the Federal Register in August 2025, and as of October 2026 the final rule sits in White House OIRA review, with publication expected late 2026 into 2027 and staggered compliance dates after that. Until it lands, large-site BVLOS runs on individual waivers and exemptions.
What the owner's paperwork needs
Aviation liability insurance naming the site, a documented pre-flight and emergency procedure, airspace authorization records, and pilot certificate numbers on file. Lenders and insurers increasingly ask for this before accepting drone-sourced evidence in a claim.
Rules change. Verify current requirements against the FAA directly before an engagement; this page is reference material, not legal or regulatory advice.
Read the rules at the source
- FAA — Part 107 rules for commercial drone operators and Remote ID requirements.
- FAA — Part 108 beyond-visual-line-of-sight proposed rule, published in the Federal Register on 7 August 2025; final rule under OIRA review as of October 2026.
Last reviewed 6 October 2026. Reference material, not legal or regulatory advice.